Highway 6 - Section 3
Length
BR 304 - 72.5 meters, UP 202 - 90 meters
Superstucture Width
BR 304 - 12.3 meters, UP 202 - 13.8 meters
Superstucture height
BR 304 - 1.5 meters, UP 202 - 0.8 meters
Main span
BR 304 - 32.5 meters (3 spans)
Planning time
9 month (under construction)
Client
Shapir Civil and Marine Engineering – Impresa Pizzarotti – Highway 6 Joint Venture
Structures
Bridges









Our Solution
ViaBridges was contracted to construct two bridges in the North Y of section no.3 on Highway 6.
BR-304 are two pre-tension U shape girder parallel bridges, 72.5 meters long, 3 spans, the main span is 32.5 meters, 12.3 meters width each. The bridges carry Road no. 75 over the Kishon River.
UP-202 is a 90-meter long underpass, 13.8 meters width, the upper road pass over transversal reinforced concrete beams in a 570 skew.